The LIPA Ruland Road 138 kV Substation has long been identified as a key Point of Interconnection for Offshore Wind. Anbaric has been developing this project for years with the assistance of Hallen Construction’s expertise.

Site Control

Anbaric has an option agreement for 3.5 acres at a parcel located 3000 feet from Ruland Road for a converter station location.

Routing

The transmission line coming from the lease area will make landfall at Jones Beach and follow a 17.7 mile buried route to the converter station location. The route is completed surveyed with utilities located, centerline construction drawings, and HDD’s completed.

Interconnection Position

Anbaric has both 800 MW and 1200 MW interconnection positions which have completed SRIS studies, and expect to enter NYISO Class Year 2022 in Q3 2022.

Permitting

Work to submit an amended Article VII is in progress. Pre-application meetings have been completed, with an expectation file in early Q2 2022.